|
Newsletter - December 2001 This is the first bi-monthly newsletter charting progress on the E1 restoration. In each newsletter we will endeavour to keep ESR members, appeal donors and anyone who has an interest in the E1 informed on the progress and problems in carrying out the overhaul. The Boiler
Just
to recap on the present situation, during the summer a great deal of progress
was made in stripping the boiler of all fittings and removing the tubes. The
foundation ring rivets were drilled out by Graham and Dick Pearce as far as
possible with the boiler still in the frames, but the boiler had to be lifted
out to finish the job. For the boiler lift, courtesy of Riley Crane Hire, we had
a beautiful sunny day and a nice picture of the event subsequently appeared in
Steam Railway. The lift was tricky because the boiler had to be rolled over onto
its side, and during this manoeuvre the pile of sleepers taking the weight
decided to spontaneously reorganise themselves (see photo of Graham “I
didn’t drop it!” McCarthy)!
After the last of the rivets was removed the foundation ring could be
extracted. This was far from simple as there was no way to get behind it to
drive it out and years of accumulated rust and sludge wasn’t letting go that
easily. Up stepped Jeff Bown and with the aid of several improvised pullers, a
big hammer and about two hours of loud banging the foundation ring dropped out. We could now see exactly what the state of the firebox was. Boiler
Inspector John Glaze was called in to assess exactly what repairs were required
and the result was some good news and some bad. The most obvious defect was that
many of the stays were not at right angles to the plates as they should be.
Greatly increased stresses would result and this was undoubtedly the reason for
a number of stay failures. Several stays in the bottom row were found to have
fractured. Since there was no sign of the inner firebox moving, the error must
have occurred when the stays were last installed. The good news was mainly that the copper firebox is better than thought
and is reusable with some copper weld repairs, which should reduce the cost of
the overhaul considerably. Some grooving above the foundation ring was apparent and the backhead,
which has been heavily welded, will also need to be repaired. The foundation
ring itself looks to be OK. The front tubeplate had already been condemned due
to wastage at the bottom. At this point a decision had to be made on how the work would be carried
out and funded. Many Railways would not consider taking on such boiler repairs
as the work required is heavy, needs good facilities and a lot of volunteer
effort and skill. However, the cost savings in doing as much as possible
ourselves are potentially large. After considering the work involved and the
resources available it was decided to give it a go. Subsequently the smokebox has been removed and work has started in
removing the stays. Since a large amount of heavy drilling will be needed for
this job, we looked around for a better drill and decided to buy one with a
magnetic base which would ease the task considerably. This will also be used in
a number of other jobs such as drilling large plates which are too large to fit
under the radial drill. Valves and Cylinders
In service the E1 suffered from an oscillating motion which despite the
best efforts and all the brain power of the loco shed could not be cured. A key
part of the examination of the valves was therefore to look for any fault which
might cause this. The cylinder covers, valves and pistons were removed to permit
the cylinders and valve ports to be inspected. With the valves removed it was noticed that the valve seats had worn by
about 12 thou at each end. This could allow the valve to rock on the inside
exhaust valve seat face and admit steam to both ends of the cylinder at once. If
this permitted steam to enter the cylinders too early in the cycle it could very
well be the cause of the oscillation. Clearly the valve seats have to be machined flat again but access to them
is very restricted. Originally the cylinder block, which is in two halves, would
have been machined off the loco making access to the seats easy. But to extract
the five ton block from the frames, possibly for the first time since the loco
was built, split it and put it back again after machining would not be a Sunday
afternoon job to say the least! An alternative method has been devised by Steve
Masters which involves a special purpose machine to enable the seats to be
machined in situ. Currently the machine has been designed and is being
manufactured in the workshops. The cylinder bores, pistons and rings were found to be in good condition
and the lubrication system seems to have worked well. Motion
The motion has been dismantled and inspected for wear. The big ends were
found to have a ‘novel’ repair which certainly needs attention before being
refitted. The crosshead slipper blocks along with the eccentric and big end
bearings require re-white metalling and machining. The axle boxes were found to be in good condition with little play
between the horn guides. Unfortunately it’s the horn guides that are moving!
The bolts holding them to the frames will be driven out, the holes reamed out to
a larger size and new interference fit bolts fitted. The springs are in good shape although part of the buckle will have to be
replaced on the two rear springs due to banana shaped holes having formed. Appeal
The ESR has made a number of minor appeals for donations but has never
seriously addressed fund raising before. The amount of money needed, and fairly
quickly, is substantial but there are many similar schemes in railway
preservation that have been successful in raising much larger sums. An
attractive package has therefore been put together offering a range of benefits
in return for cash donations or gift aid (formerly called covenants). The appeal is being launched in the railway press and being circulated to
ESR members. It is also intended to approach special interest groups whose
membership may have a particular interest in the loco. A station display was put
up at Cranmore in time for the Hertfordshire Railtour visit in November. The
appeal has got off to a good start with a donation of £350 which has helped pay
for the magnetic drill.
|